HOW TO ESTIMATECONCRETE COST

Concrete paintings in a venture typically holds the most weightage in terms of universal cost and work amount. It therefore turns into an important step to calculate the concrete associated costs whilst making ready a assignment estimate. The price of concrete depends upon the cost of materials, mix design, group of workers, and equipment. In this newsletter we calculate the price of one cubic meter of concrete and different expenses that occur within the preparations of concrete.

for watch detailed video about HOW TO ESTIMATECONCRETE COST, see below. for getting daily updates follow our facebook page and click see first option in following button. if you interested this. give this post to your friends and relatives.for more videos, subscribe now:Civil Engineer Malayalam

Factors that Affect the Cost of Concrete

1. Material Costs

Costs of materials and supplies and the associated delivery fees affect the value of any concrete production assignment.

2. Labor Rates

The local hard work prices or wages targeted by way of the kingdom have an effect on the expenditure of a assignment.

3. Site Conditions

The area and the earlier website online circumstance affect the cost of the project and urban. Poor soil first-class, wetlands, contamination, software, environmental and site visitors problems are few examples on this category.

4. Schedule

If the mission agenda is simply too quick for the form of work worried, then task fees have a tendency to be on the higher facet. This is particularly real for initiatives with a widespread liquidated harm clause of their contracts.

5. Contingency

A 10% contingency fund of the full expenditure is normally set aside through cement contractors to cover unforeseen fees. However, inflation and scarcity of materials and components may require a better contingency of the range of 15-20%.

Calculation of Cost for 1m3 of Concrete

Let’s do not forget the concrete mix of M15 (1:1.5:3), where, 1 is the part of cement, 1.Five is the part of first-class aggregates and three is the a part of coarse aggregates of most length of 20mm. The water-cement ratio required for mixing of concrete is taken as 0.45.

1. Assumptions:

Bulk Density:

1. Cement = 1500 kg/m3
2. Sand = 1700 kg/m3
3. Coarse aggregates = 1650 kg/m3

2. Calculation of Materials for

1m3 Concrete
Dry volume = Wet Volume X 1.Fifty four
Volume of cement required = (Dry quantity X Cement ratio)/ Sum of ratio
Volume of Cement = (1 X 1.Fifty four)/(1+1.5+3)
= 1.Fifty four/5.Five
= 0.28m3
Weight of the cement = zero.28 X 1500
= 420 kg.

Volume of Sand = (1.Five X 1.54)/(1+1.Five+3)
= 2.31/five.5
= zero.42m3
Weight of the Sand = 0.Forty two X 1700
= 714 kg.

Volume of Course Aggregate= (three X 1.Fifty four)/(1+1.Five+three)
= four.Sixty two/5.Five
= 0.84m3
Weight of the Course Aggregate = 0.Eighty four X 1650
= 1386 kg.

3. Cost Calculation
Cost of cement for 1 m3 =
No of Bags = 420/50
=eight.Four Bags
As in line with ultra-modern marketplace price, value of 1 bag of cement is taken as Rs: 450
= 8.4 X 450
= 4200 Rs

Cost of sand for 1 m3 =
As consistent with state-of-the-art marketplace rate, price of one m3 of sand is taken as Rs: 1400
= zero.42 X 1400
= 588 Rs

Cost of direction combination for 1 m3 =
As consistent with contemporary marketplace charge, fee of 1m3 of route aggregate is taken as Rs.2400
= 0.Eighty four X 2400
= 2016 Rs

Therefore overall value of 1m3 of M15 concrete is
=Cost of cement + sand + route mixture
= 4200 + 588 + 2016
Say Rs 6400

Advertisement

Related Articles

Back to top button

Adblock Detected

Please disable adblocker for using this site.